Vapour barrier
or vapour retarder.
Behind the plasterboard of a lining or a rafter slope, a simple membrane decides the lifespan of the insulation. Vapour barrier, vapour retarder or humidity-variable membrane: the choice is read in a single value, the Sd, and success is decided in the junctions. Here are the rules of the DTUs and of the CSTB installation guide, and what our quotes provide for.
Why a membrane behind the plasterboard
Cooking, showering, breathing: all of this loads the indoor air with water vapour. ADEME gives telling orders of magnitude: a pan of boiling water releases about 400 g of water per hour, a hot shower 200 g. Ventilation removes part of it; the rest tries to cross walls and ceilings to reach the outside.
During this crossing, the vapour meets increasingly cold layers. Its relative humidity climbs, to the point where it becomes liquid water again in the heart of the insulation or against the roof frame. The CSTB installation guide, published by ADEME in 2023, describes the consequences: materials that lose their performance, weakened timber, mould that spreads into the rooms.
The membrane therefore fulfils two functions, which ADEME distinguishes: reducing the amount of vapour that enters the wall, and cutting off unwanted air leaks through the junctions. Fitted without interruption around the heated volume, it does both. Pierced or poorly connected, it does neither.
Vapour barrier, vapour retarder, humidity-variable: everything depends on the Sd
The Sd quantifies a material's resistance to the passage of vapour. It is expressed in metres: it is the thickness of air that would slow the vapour as much as the product. It is obtained by multiplying the material's μ coefficient by its thickness: a 12 mm OSB board, with μ = 217, thus shows an Sd of about 2.6 m.
Standard NF DTU 31.2, revised in May 2019 for timber-frame houses, draws the line: a vapour retarder has an Sd of between 1 and 18 m, a vapour barrier an Sd of 18 m or more. So-called humidity-variable membranes have no single value: their Sd changes with the ambient humidity, and may even differ depending on the direction of vapour flow. Their fitting then falls under their Avis technique (technical approval), not just the general rules.
| Membrane | Sd value | Behaviour | In our 2024-2026 quotes |
|---|---|---|---|
| Vapour barrier | 18 m or more (NF DTU 31.2) | Stops almost all vapour coming from the inside | Timber-frame walls, with sealing adhesive at the junctions (8 quotes) |
| Vapour retarder | From 1 m to less than 18 m (NF DTU 31.2) | Lets part of the vapour through | Screen fitted under the furring strips of ceilings under the loft |
| Humidity-variable membrane | Variable with humidity: from 0.4 to 25 m for the one in our quotes (manufacturer's data sheet) | Reacts to the humidity level; fitting defined by its Avis technique | Linings and ceilings, under the Isover Vario reference or equivalent (23 quotes) |
A vapour retarder is not a cut-price vapour barrier. It is chosen when the wall must be able to dry towards the inside, or when its outer layers themselves let vapour through. On an old stone or cob wall, it is the rule, as our guide to insulating walls from the inside explains.
Always on the warm side of the insulation
The membrane is fitted on the room side, between the insulation and the plasterboard or any other interior facing. This is where it stops the vapour, before it reaches the cold layers of the wall.
When the insulation is fitted in two layers, the membrane can slip between them, on a condition set by the CSTB guide: the inner layer must not exceed a third of the wall's total thermal resistance, and a quarter in a very cold zone. Thicker, it would put the membrane too close to the cold.
The same guide describes another arrangement: a service void left between the membrane and the plasterboard. It takes ducts and pipes, and protects the membrane if the board is pierced later. In a timber-frame house, NF DTU 31.2 even makes it essential.
Timber frame: the factor-5 rule
On a timber-frame wall, the interior membrane is not chosen in isolation: it depends on what is on the outside. NF DTU 31.2 allows two methods. One requires a vapour barrier with an Sd of at least 18 m. The other, known as the "factor 5", accepts a more open wall provided that the Sd on the inside is at least five times higher than that of the outer layers, bracing board and weather barrier included.
An educational sheet on this standard, published by the Ministry of National Education, gives two examples. A 9 mm OSB (Sd 1.5 m) and a flexible weather barrier (Sd 0.18 m) total 1.68 m: the interior vapour retarder must exceed 1.68 × 5, i.e. 8.4 m. With bracing in fibreboard and a rigid weather barrier, also in fibre, the total falls to 0.46 m, and 2.3 m is enough.
This calculation makes it possible to build so-called breathable walls without exposing the frame timbers to condensation. In our timber-frame wall quotes, the membrane is a vapour barrier bonded at the junctions with a sealing adhesive.
Is a membrane needed everywhere?
Almost. ADEME considers it necessary, on the heated-volume side, for insulating a timber-frame house, and for the roof spaces (unconverted or converted) of houses in a very cold zone, except unconverted lofts over a concrete floor. Everywhere else, it strongly recommends it for airtightness.
In Savoie and Haute-Savoie, the question therefore rarely arises in that form. Our teams do not ask whether a membrane is needed, but which one: a vapour barrier on a timber frame, a smart (humidity-variable) membrane on an internal lining or a ceiling, a humidity-variable vapour control layer on old masonry that must keep drying out.
Unconverted lofts follow their own logic. ADEME places the membrane on the attic floor, before the insulation is rolled out or blown in. When the ceiling is redone, the CSTB positions it just above the plasterboard, and the hangers that pass through it receive dedicated accessories. Our guide to unconverted lofts covers this case in detail.
And what about the kraft facing on wool rolls?
Many mineral wools are sold with a kraft paper facing. The CSTB guide is clear: on a wall or a rafter slope, this kraft, even when taped on site, is not considered a vapour-sealing layer. It does not replace a continuous, bonded membrane. Most of our internal lining specifications therefore combine a faced wool with a separate membrane, as our comparison glass wool or rock wool points out.
The mistakes that cancel out the membrane
A poorly joined membrane is hardly better than no membrane at all. The defects to watch for come up again and again from one site to the next:
- Strips simply laid over one another. The CSTB requires an overlap of at least 100 mm between two strips, and a compatible adhesive tape to restore continuity.
- Forgotten penetrations. Cables, electrical conduits, ventilation ducts and hangers each receive an accessory: adhesive grommet, tape or sealant-adhesive from the same system.
- Poorly connected windows and doors. On a timber frame, the membrane is folded at least 100 mm into the opening, or connected to the frame by a tape with at least an equivalent Sd.
- Adhesives from another system. The CSTB points out that a membrane and its accessories are assessed together, and that this assessment only holds with those same accessories.
- A sealed membrane on an old wall. Masonry that takes up moisture from the ground must dry towards the inside; an airtight vapour barrier creates a condensation zone there.
- A damp wall or no ventilation. ADEME prohibits insulating a wall showing signs of damp, and the CSTB requires ventilation compatible with an envelope that has become airtight.
The CSTB installation guide, produced on the initiative of the housing, planning and landscape directorate, details the common junctions with diagrams: wall base, intermediate floor, window or door, flue, loft hatch.
What a vapour barrier costs
We reviewed our 2024-2026 quotes in Savoie and Haute-Savoie: the membrane appears in 143 lines across 36 quotes, and it is never priced on its own. It is part of the per-square-metre price of the work that carries it, with its adhesives and the treatment of penetrations. No quote therefore allows the price of the installed membrane to be isolated honestly, and we do not publish one.
Here are the two items of work that include it most often, with the prices published in our guides:
| Work item | Membrane specified in the description | Price per m² excl. VAT, membrane included | Detail |
|---|---|---|---|
| Insulating internal lining on a metal frame | Bonded smart-membrane screen, or kraft-faced wool depending on the quote | €75 to €90 | Price of plasterboard per m² |
| Ceiling under the roof space, insulation rolled out above | Vapour control screen under the furring strips | €105 to €115 | Price of a suspended ceiling |
To compare two quotes, look less at the price than at the description: type of membrane and Sd value, brand and reference, jointing adhesives, treatment of penetrations and of windows and doors. A line that says only "vapour barrier" tells you very little about what will be installed.
The choice of membrane goes hand in hand with the choice of insulation: our guide Thermal insulation: which one to choose? compares the insulation families, notably on how they behave with water vapour.
What we check before closing up
Insulation, membrane and plasterboard are fitted by our salaried plasterboard fitters, the conduits by our electricians: penetrations are planned before the plasterboard goes up.
A membrane suited to the wall
Vapour barrier, vapour control layer or smart membrane, decided together with the insulation and the substrate, with the reference written into the quote.
Warm side
Membrane on the room side, or between two layers of insulation in line with the one-third rule.
Strips and adhesives
Overlap of at least 100 mm, adhesive tapes from the same system, carefully finished joints at walls and floors.
Penetrations treated
Cables, conduits, ventilation ducts and hangers fitted with compatible accessories, one by one.
Service void
Air gap between membrane and plasterboard where the wall requires it, for services and future drilling.
Controlled ventilation
An airtight envelope must be ventilated: we check the existing ventilation before insulating.
Find out more
Where our teams insulate
Membranes and insulation fitted by our teams from Aix-les-Bains and Annecy, from Lac du Bourget to the resorts of Haute-Savoie.
Frequently asked questions · Vapour barrier
A membrane fitted
without a hole.
Free visit and quote: we state the chosen membrane, its Sd value and the treatment of the joints, line by line.