Renovating your
bathroom.

A bathroom is redone in a precise order: what is hidden in the walls and under the floor comes before what is seen. Here are the stages of a complete job, how long it lasts, and the prices taken from our own 2024-2026 quotes in Savoie and Haute-Savoie, item by item.

≈ 10 400 €
Median budget excl. VAT for a 5 m² shower room, calculated from our quotes
2 to 3 wks
Average duration of a completely redone bathroom
10 %
VAT on a renovation in a home over two years old
0 €
Visit, survey and quote for your bathroom

Freshening up or redoing everything: two different jobs

Changing a vanity unit, repainting, replacing a mixer tap: this work takes a day or two and does not touch the pipework. A complete renovation is a different job. The room is stripped back to bare walls, the supplies, drains, electrics and waterproofing are reworked, then everything is rebuilt. Neither the budget nor the duration is of the same order.

What decides between the two is the condition of what you cannot see. Tiling that sounds hollow, blackened joints at the foot of the shower, a smell of damp or a stain on the ceiling of the room below almost always betray an old leak. A simple freshening up would cover it over without fixing it.

The layout matters too. Keeping the shower, WC and basin where they are limits the plumbing. Moving a WC means connecting to the stack with a sufficient fall, which is not always possible without raising the floor or going through the neighbouring room.

The stages of a complete renovation, in order

1. Survey and diagnosis. We measure the room, locate the water supply, the drainage stack, the electrical panel and the ventilation, and probe the partitions and floor. It is this survey that tells you, for example, whether a level-access shower is feasible in the position you want.

2. Removal and demolition. Fittings, wall tiles, floor covering and sometimes partitions go to the waste site. In an old building, this is also when the real condition of the floor is discovered.

3. Plumbing. Our plumbers create the new cold and hot water supplies and the drains, with the falls required to the stack. The support frame for the wall-hung WC is fitted at this stage, before any partition.

4. Electrics. Our electricians run the lines for the lighting, sockets and towel rail. The NF C 15-100 standard divides the room into zones around the shower and the bath: they set what can be installed, and where.

5. Plastering. Our plasterers build the partitions and casings in moisture-resistant boards, box in the pipework and, if needed, create a suspended ceiling to recess spotlights.

6. Waterproofing. On the walls and floor of the shower area, an under-tile waterproofing system (SPEC) is applied in coats, with tapes in the corners. Once the job is finished, nobody sees it any more: yet it is what prevents water damage.

7. Tiling and wall tiles. Our tilers lay the floor, the shower tray or tiled shower, then the wall tiles. The setting times of the adhesive and grout impose a rhythm that must not be compressed.

8. Fittings and finishes. Screen, shower column, WC pan, vanity unit, towel rail; then our painters treat the ceiling and the untiled parts.

9. Ventilation and testing. A bathroom produces a lot of steam: without extraction, it condenses on cold walls and ends up in the joints. We connect a vent to the existing mechanical ventilation (VMC) or fit an extractor, then we turn the water on and check every connection before handing the room back to you.

How long the job takes

Allow on average two to three weeks for a completely redone bathroom, removal included. The duration runs longer when a partition is moved, when the floor has to be repaired, or when a made-to-measure fitting has a manufacturing lead time.

During this time, the room cannot be used. In a house with only one bathroom, this is the first point to organise with us: keeping a WC in service for as long as possible, or phasing the work to keep a water point. In a co-owned building, also inform the managing agent if the work affects the shared water or drainage stacks.

What really saves time: choosing the fittings before the start. The plumbing and wall tiles are set to the exact dimensions of the shower tray, the unit and the support frame; an item delivered late blocks every stage that follows.

The prices taken from our quotes, item by item

These ranges are taken from our 2024-2026 quotes in Savoie and Haute-Savoie. For each item, we took the price charged on each job, then kept the spread between the cheapest quarter and the most expensive quarter. Amounts exclude VAT, with supply and fitting included in the great majority of lines.

ItemUnitPrice found, excl. VATProjects
Removal of existing fittingsthe bathroom€500 to €1,3007
Demolition of wall tilesm²€20 to €405
New water supplies and drains (shower and WC)the bathroom€400 to €1,2005
Under-tile waterproofing of the shower (SPEC)lump sum€500 to €7006
Shower trayeach€700 to €1,50035
Shower column or mixereach€750 to €1,50026
Shower screeneach€400 to €90020
Wall-hung WC with support frameeach€700 to €90044
Vanity uniteach€700 to €1,50042
Batheach€800 to €1,85032
Wall tilesm²€90 to €11515
Floor tilingm²€100 to €11517
Towel raileach€250 to €8504

An item does not always appear on its own on a quote: the shower tray, screen and column are sometimes priced together, and the fitting sometimes appears on a separate labour line. That is why we think in ranges, and why two quotes can only be compared on an identical scope. The widest gaps, from single to double, concern the fittings: it is the range chosen that explains them, not the fitting work.

Example: the budget for a 5 m² shower room

To give an order of magnitude, we put these prices together on a typical shower room of about 5 m²: removal of what is there, 15 m² of wall tiles demolished then relaid, 5 m² of floor tiling, new supplies and drains, shower waterproofing, shower tray, screen, shower column, wall-hung WC, vanity unit, towel rail, a set of spotlights, two sockets and ceiling painting. This is a calculation, not a real job: your quote will start from your room.

ScenarioTotal excl. VATTotal incl. VAT (10% VAT)
Price of the cheapest quarter of our quotes≈ 7 600 €≈ 8 400 €
Median price≈ 10 400 €≈ 11 500 €
Price of the most expensive quarter of our quotes≈ 13 800 €≈ 15 200 €

These amounts stay within the range of €6,000 to €15,000 that we give for a 4 to 6 m² bathroom on our pages for Aix-les-Bains, Annecy and Chambéry. Adding a bath next to the shower represents €800 to €1,850 excl. VAT extra; a larger room mainly increases the wall tiles and the floor, invoiced per square metre.

We do not give a price per square metre for a bathroom, for a simple reason: in a small room, the fittings weigh more than the area. A 4 m² shower room and an 8 m² bathroom often receive the same WC, the same shower column and the same unit. Brought down to the square metre, the price of the small one looks much higher, without it costing more to build.

What makes the cost of a bathroom vary

The layout. Leaving the supplies and the stack where they are remains the clearest saving. Moving a shower to the other end of the room means new drains, sometimes a screed to bury the pipes and create the fall.

The type of shower. An extra-flat shower tray is fitted faster than a tiled shower, which requires more work on falls and waterproofing. On the three jobs where we priced a tiled shower tray or channel, the supply alone was between about €1,500 and €2,150 excl. VAT. A guide devoted to the walk-in shower will follow, as will a guide to the wall-hung WC, present on 44 of the jobs in our quotes.

The range of fittings. The table shows it: a shower column, a unit or a screen can cost double from one model to another, for an identical fitting. This is the item on which you keep control.

Discoveries during demolition. A timber floor damaged by an old leak, a partition too fragile to carry wall tiles, old pipework to replace: the prior survey reduces this risk, without being able to eliminate it. We flag it in the quote rather than have it discovered on the invoice.

In Savoie and Haute-Savoie: old buildings, chalets, second homes

In the old buildings of Aix-les-Bains or Chambéry, the bathroom has often been added after the fact, in a former closet or a section of corridor, on a timber floor and with small-diameter drains. Before promising a level-access shower, we check the thickness available under the floor and the route to the stack.

In a chalet, a tiled shower on a timber floor requires a recess in the floor or a slight raising, and particularly careful waterproofing: wood moves, wall tiles do not. In second homes in the resorts, the job is also timed around the periods when the property is unoccupied.

Finally, redoing a bathroom is the right moment to deal with damp. In an old house with cold walls, steam condenses where the insulation is missing. If insulating the walls from the inside is planned in the coming years, it is better to include it before the wall tiles than to break up a new bathroom.

VAT on a bathroom: 10% in most cases

In a home completed more than two years ago, renovating a bathroom is subject to the 10% rate: labour, materials, and fittings built into the structure such as the shower tray, the wall-hung WC or a fixed unit. A freestanding unit stays at the standard rate of 20%, even if it appears on the same quote, as do materials and fittings that you buy yourself.

Since 1 March 2025, there is no longer any need to fill in a certificate: you certify that the conditions for the reduced rate are met by a statement on the quote or invoice. All cases, including that of recent homes, are detailed in our guide to VAT on renovation work.

Our projects around the lake

All projects →

From our Aix-les-Bains office, our sites stretch from the shores of Lac du Bourget to the Val d'Arly. Here are some recent projects.

How we carry out a bathroom

One company, our own craftsmen, a quote that reads clearly line by line.

Visit and survey

Measurements, locating the water supply, the stack and the panel, probing the substrates. A bathroom cannot be priced over the phone.

Plan and choice of fittings

Layout, wall-tile setting-out, selection of the shower tray, unit and WC before the start, so that every dimension is known.

Item-by-item quote

Removal, plumbing, electrics, waterproofing, tiling, fittings: every line is separate and comparable.

Our salaried craftsmen

The company's plumbers, electricians, plasterers, tilers and painters each carry out their own part of the job, in their own trade.

Waterproofing check

Our site manager checks the SPEC in the shower area before the wall tiles cover it: afterwards, it would be too late.

Water test and handover

Tests of every connection and of the drain, then handover of the room with you.

Where we renovate bathrooms

Visit and quote prepared from our offices in Aix-les-Bains and Annecy, across the two Savoie départements.

Frequently asked questions · Bathroom renovation

How much does a complete bathroom renovation cost?
For a shower room of about 5 m² completely redone (shower, wall-hung WC, vanity unit, wall tiles and floor), our prices taken from our 2024-2026 quotes give about €7,600 to €13,800 excl. VAT, i.e. €8,400 to €15,200 incl. VAT at 10% VAT. The amount depends mainly on the layout (keeping or moving the water supplies) and on the range of fittings.
How long does the work take?
Allow on average two to three weeks for a completely redone bathroom, removal included. The job runs longer if a partition is moved, if the floor has to be repaired or if a made-to-measure fitting has a manufacturing lead time. Choosing the fittings before the start avoids waiting.
What VAT rate applies?
In a home completed more than two years ago, work and fittings built into the structure (shower tray, wall-hung WC, fixed vanity unit) are subject to the 10% rate. A freestanding unit, or fittings that you buy yourself, remain at 20%. Since 1 March 2025, a statement on the quote or invoice replaces the certificate.
Can a bath be replaced with a shower?
Yes, it is one of the most frequent requests. You need to check that the waste pipe keeps a sufficient fall to the stack, then choose between an extra-flat shower tray and a tiled shower. In both cases, waterproofing under the tiles in the shower area is essential.
Why is waterproofing under the tiles essential?
Because wall tiles and their joints are not waterproof. Water that passes through them soaks the partition or the floor, and ends up as water damage in your home or in the neighbour's below. The under-tile waterproofing system (SPEC) is applied before the wall tiles; on our quotes, it represents about €500 to €700 excl. VAT for a shower area.
Is the quote free?
Yes. We come to see the room, measure it and give you a detailed quote, at no cost and without obligation. Every item is priced separately in it, from removal to finishes, so that you can compare it line by line.